To the news list
In the second stage, in section 5-A, the installation of windows is completed
July 12, 2021
RIEL Real Estate Corporation reports that the construction of Riel City residential complex is actively pursued. According to the project manager Roman Dmytrakh, the builders in the 5-A section’s second stage are completing the installation of windows.
It is also reported that in section 1-B, the monolithic work and the parapets filling are over, the walls are being laid on the seventh and eighth floors.
Besides, we report that in section 1, the fourth floor slab casting has been performed and the vertical of the fifth floor is being erected.
You can find out in details about the construction progress and the terms of purchasing an apartment in Riel City RC in our sales departments, contacts at the link.