Screeds have been poured in the fourth stage in the building 4-B
RIEL Real Estate Corporation is actively working on the completion of the Riel City Residential Complex.
In the fourth stage, builders have completed the screeds in the building 4-B, and the installation of elevators in the buildings 2-B and 5-B is underway. At the same time, screeds are being poured in the boiler room.
The boiler house in the second stage has already been launched, and the final works are bringing the building closer to commissioning.

The construction of the educational institution continues as well: the monolithic columns of the second floor are being completed at the site.