Riel Сity RC: in sections 1-B of the second stage, the floor slab casting is completed on the 10th floor
RIEL Real Estate Corporation reports that builders actively pursue the construction of the Riel City residential complex. In the second stage of section 1-B, the specialists have completed the slab of the 10th floor and are erecting the vertical of the 11th floor. Blockwork is performed on the fifth and sixth floors. This was announced by the project manager Roman Dmytrakh.
It is also reported that in section 5-A, the roofing has been completed.
It is also reported that in section 1, a slab of the second floor is performed, the vertical of the third floor is being erected.