Interior finishing and engineering works continue in the fourth stage

May 15, 2025

RIEL developer continues construction of the Riel City Residential Complex in Lviv.

Interior finishing and engineering works are continuing in the fourth stage. Plastering works have been completed in section 2-B and doors are being installed.

In section 5-B, plastering of the premises is continuing. A heating main is also being installed to the boiler room, which will provide independent heating in the buildings.

At the same time, construction of the school continues: monolithic work has been completed and blockwork is underway on the first floor.

We would like to remind you that the second stage of the complex has already been commissioned.

The Riel City Residential Complex is a large-scale comfort-class project being implemented by the RIEL Development Company in Lviv at 8 Rudnenska Street, in Zaliznychnyi District. The complex integrates modern architecture, well-thought-out infrastructure and a convenient location.

For more information about available layouts and terms of purchase, please contact the sales department. Contact details can be found at link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.